A rush order and a shared component change: three records to check
A rush fan order raises three separate questions: available parts, free station time and engineering approval. The figures below come from three separate test-factory scenarios.
1. The frozen schedule
Assembly needs 772 minutes against 480 available, a 292-minute gap. Open both operations: one has a reservation and the other a recorded block. Identify the people, station and slot before proposing overtime or a sequence change. The gap alone does not establish a missed customer delivery.
Open the related evidence →2. The engineering change
Twenty models share one board, but only five may use its replacement. Non-interchangeable boards need distinct item codes. In the sample, 100 old boards in stock do not cover a shortage of five new boards. Separate the changed BOM from affected parent models so the other fifteen keep the old part.
Open the related evidence →3. The requisition and released work order
Distinguish ordered quantities from open requisitions and quantities retained for other models. On the floor, compare the frozen material on an existing work order with the effective package on a new one. Request an issue from each and reconcile the item codes and purchase follow-ups to the approved scope.
Open the related evidence →