Rush orders and shared components: checking two assembly lines

Work from a shared control board through effective BOMs, available stock, supply dates and resource reservations.

Suppose two fan models share one controller. When a rush order arrives, confirm its quantity and requested date, then compare the effective BOMs and frozen requirements of existing work orders. Stock on hand cannot be allocated twice.

Use MRP to identify uncovered demand. Purchasing checks open receipts; warehouse staff check availability, reservations and inspection status. For feasible orders, compare assembly capacity, test equipment, shifts and changeovers.

Before approval, compare how alternatives affect existing orders and customer commitments. Feed actual starts and output back into delivery follow-up. The example describes a review sequence; the resulting date depends on the factory’s records.